Change-Order Builder

Price added work, apply agreed credits, and print a change worksheet with scope and schedule effects.

Shared shop rates

Save rates once and apply them when needed. Labor is cost per productive person-hour; overhead is separate. Values are stored only in this browser.

Your worksheet

Example inputs. Replace them with your shop’s numbers.

Added materials and purchased work

Use positive additions here. Enter reductions as an agreed selling-price credit above.

Results

This worksheet records the commercial change. Reference your signed agreement for approval and payment requirements. Printing an approval name does not create an electronic signature.

Change approval

Customer signature / date: ____________________________________

Shop representative / date: __________________________________

How this is calculated

  • Added cost = line-item costs + additional person-hours × (labor rate + overhead rate) + subcontract cost.
  • Added charge = added cost ÷ (1 − margin). Net change = added charge − agreed customer credit.
  • Revised contract = original contract + net change. All amounts exclude tax.

All money inputs use USD. Calculations retain full precision; displayed amounts are rounded. Drafts save on this device when browser storage is available. Export your worksheet to keep a separate copy.